'''Tasks'''
'''Tasks'''


Complete modification of the Paramount to use a Galil motion controller
Done: Complete modification of the Paramount to use a Galil motion controller


Complete Mt. Kent echelle for shipment by March 31, 2014
Complete Mt. Kent echelle for shipment by September 15, 2015


Complete software pipeline for remote/autonomous operation of CDK20 photometry
Complete software pipeline for remote/autonomous operation of CDK20 photometry


Complete addition of XPA to XmTel and XmCCD for remote operation
Done: Complete addition of XPA to XmTel and XmCCD for remote operation


Design, build, and install remotely operated mirror covers  
Deferred: Design, build, and install remotely operated mirror covers  


Add wireless Sirius dome opening relay transponders
Done: Improve Sirius dome opening relay operation


Add dropline RC24 dome shutter operation
Done: Add dropline RC24 dome shutter operation


Add heater to CDK20 secondary
Deferred: Add heater to CDK20 secondary


Complete prototype Moore echelle for testing in spring 2014
Complete prototype Moore echelle for testing in fall 2015




'''Notes'''
'''Notes'''


Roll roof remote operation requires wiring limit switches.
Roll roof motor relays replaced and interlocks rewired in preparation for remote operations.


== Software ==
== Software ==

Revision as of 05:57, 15 August 2015

This is the "to do" list for the Shared Skies project.

Last update: March 9, 2014


Mt. Kent

Tasks

Done: Install RFID encoder and motors for the dome for CDK700

Done: Install new computer in CDK700 dome (awaits delivery from US)

Done: Install FSQ106 in middle dome (awaits delivery from US)

Ship: Replacement power switch for CDK20S dome

Software: Web interface for CDK20S and Takahashi

Software: Driver for Planewave server on CDK700


Notes

Digiloggers unit is back ordered

Moore

Tasks

Done: Complete modification of the Paramount to use a Galil motion controller

Complete Mt. Kent echelle for shipment by September 15, 2015

Complete software pipeline for remote/autonomous operation of CDK20 photometry

Done: Complete addition of XPA to XmTel and XmCCD for remote operation

Deferred: Design, build, and install remotely operated mirror covers

Done: Improve Sirius dome opening relay operation

Done: Add dropline RC24 dome shutter operation

Deferred: Add heater to CDK20 secondary

Complete prototype Moore echelle for testing in fall 2015


Notes

Roll roof motor relays replaced and interlocks rewired in preparation for remote operations.

Software

Remote

Integrate systems with web interface for remote operation


XmTel

Update Galil system for modified Paramount

Add XPA server


XmCCD

Update Apogee drivers for new models

Add XPA server